OMKAR 1973 TOWER A
Developers

Omkar 1973 Tower A

WorliM/s - Omkar Reality2016
Visit Client Website
ClientM/s - Omkar Reality
LocationWorli
IndustryDevelopers
System TypeVRV / VRF
Capacity8000 HP
MEP ConsultantBuro Happold
Completed2016
Duration12 Months
Project Overview

The brief

Completed low side installation work for a 4000 TR water cooled VRV system at Omkar 1973 Tower A in Worli.

Gallery

Project execution

Omkar 1973 Tower A - Final Handover
Completed

Completed Installation

Omkar 1973 Tower A - Equipment Layout
Equipment

HVAC Plant Configuration

Omkar 1973 Tower A - Duct Mounting Work
Site Progress

Duct Routing Progress

Omkar 1973 Tower A - Structural Execution
Site Progress

Site Structural Assembly

Omkar 1973 Tower A - Machinery Setup
Equipment

Daikin/Mitsubishi Condenser Units

Omkar 1973 Tower A - Testing & Commissioning
Completed

Air Balancing Testing

Planning a similar installation?

Get a costed HVAC proposal from our engineering desk.